Case Study – manufacturing filtration and ductwork system
The challenge
DBS was contracted to bring emissions from a heat treating operation below Ontario Ministry of Environment standards.
The scope of work
DBS installed 5 custom-built extraction filter systems for the oil from the heat treating operation. This was a turnkey operation and included the engineering and install of structural frame and 50 ft. stacks on the roof of the plant. DBS also designed, welded and installed all the custom ductwork to achieve the proper capturing velocity.
The results
Subsequent MOE testing proved emissions well below ministry standard - in fact in the 3 years since installing the system, Stackpole has not had one single emissions complaint. Stackpole improved the inside environment for their employees, removing significant amounts of smoke and haze from inside plant.
In addition, Stackpole has saved significant operation expenses by reducing downtime from MOE shut-downs and complaints from neighbours, and reduced maintenance and filter costs of the legacy systems that were removed. |